SOLD & CLOSED September 3, 2015

2801 Blanchard Dr Chalmette LA 70043

Featuring  Jean Lafitte Floor plan, 1515 square feet of living area 1545 Total Sq feet 3 bedrooms 2 bath home with a covered front porch.  Floor plan is open & functional with a large Master bath with over sized tub, shower and 2 walk in closets.  The St Romain team will guide you through the process and get you in your new home before you know it. 

  

2801 Blanchard Chalmette La 70043   Lot Size                 70 X 71

    Great Room          18.10 X 14.10

​    Kitchen/Dining       18.10 X 11.6

    Master                    13.11 X 13.6

    Bedroom 2              12.3 X 11.6

    Bedroom 3               9.5 X 12

                                                                  

                      

      The VIP Package includes:

  • Granite counter tops
  • Staggered height cabinetry
  • Stainless Steel, Black or White appliances
  • Tile floors in the Kitchen and Baths
  • Laminate or carpet in the den, hall and bedrooms
  • Tile shower in Master Bath
  • Choose up to 3 paint colors
  • Crown Molding in all open area
  • Exterior features all brick

 

 

 

Timeline to Build:

The homebuilding process may vary from parish to parish and builder to builder. Be sure to ask your builder about his/her specific policies and procedures.

March 6, 2015 - Filed for the Permit in the St Bernard Permit office. This usually takes 3 to 5 business days

March 12, 2015 - The Permit is ready!  Time to order the dirt!  It rained for the entire week so this process was delayed.

March 30, 2015 - Prepare site!  Time for the dirt.

March 31, 2015- The foundation is being built.

April 9, 2015 - The Slab is poured.

April 17, 2015 - The Frame is going up! - It was delayed due to a week of rain.

April 17, 2015 - Time to pick out the Brick color, Light Fixtures and Cabinets

April 27, 2015 - All Closed up.  The doors, windows, and roof decking is installed.  The rain continues to delay the process. 

May 5, 2015 - The roof is complete

May 12, 2015 - Time to start the bricks

May 13, 2015 - Time for the electrical

May 20, 2015 - The Bricks are complete

June 17, 2015 - Trim Work

June 23, 2015 - The tile is installed

June 25, 2015 - Cabinets are Installed

July 25, 2015 - Driveway is poured

July 28, 2015 - The AC is installed

August 8, 2015 - The floors are installed

August 12, 2015 - Occupancy certificate

September 3, 2015 - Act of Sale

 

 


STEP 1 Prepare site –  Time to bring in the dirt! Using a backhoe and a bulldozer, your builder will clear the lot of rocks, debris and trees for the house.  Your builder will have the lot  leveled to ensure proper drainage, and will put up wooden forms to serve as a template for the foundation, and dig the holes and trenches for plumbing.  It won't be long before you see real progress.

 

 

 

 

2801_Blanchard_Chalmette_La_70043_Foundation

STEP 2 - Form the Foundation  Now that the dirt is poured and leveled it is time to build the foundation. The footings are dug, formed and poured; the area between them is leveled and fitted with utility runs (e.g. plumbing drains); and the slab is poured.  We should start seeing some real progress.

 

 

 

 

 

Step 3: - Pour the Slab Once concrete is poured into the holes and trenches, it will need time to cure. During this period, there will be no activity on the construction site.

After the concrete is cured, the next steps are framing.

 

 

 

 

 

 

 

Step 4: Time for framing: The walls and roof  are being framed (collectively known as the shell or skeleton of the house).   You can now see the floor plan.  Now is the time to pick out the Brick color, Light Fixtures and Cabinets.  

New Construction St Bernard Parish

 

 

 

 

 

 

 

 

Step 5: All Closed up: The doors, windows and roof decking is installed.  The house can now be locked up and start working on the electrical.  Time to pick out the brick.

 

 

 

 

 

Step 6: Complete rough framing: The shell or skeleton of the house is complete.  The roof, and the bricks are complete so it is time to lock it up.  At the same time, the electrical and plumbing contractors start running pipes and wires through the interior walls, ceilings and floors. Sewer lines and vents, as well as water supply lines for each fixture, are installed. Bathtubs and one-piece shower/tub units are put in place at this point because there’s more room to maneuver large, heavy objects.

 

 

2801 Blanchard Chalmette LA 70043_New Construction

 Step 7 Interior Trim

Doors, moldings, and shelves are installed at this time. This includes doors, base boards and crown molding 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Where Do I Go Next?

3728 Gallo Dr  Chalmette LA 70043

3728 Gallo Dr Chalmette LA 70043

Featuring Jean Lefitte Floorplan, 1300 square feet of living area 3 bedrooms 2 bath home with a covers front porch. Floor plan is open & functional

Property Bin